摘要
在隧道掘进过程中造成塌方的因素很复杂,地质因素、施工因素、管理因素等均可能造成隧道塌方。正确分析塌方的原因,有针对性的处理措施是解决隧道塌方的有效处理方法。结合隧道塌方工程实例,采用注浆加固、锁脚锚杆加固拱架、喷混凝土补强、排水孔施工等综合处理方案处理复杂塌方,同时为类似工程事故的处理提供借鉴。
In the process of tunnel tunneling,geological factors,construction factors and management factors may cause tunnel collapse.Correct analysis of the primary cause of the collapse and targeted treatment measures are effective methods to solve the tunnel collapse.Combined with the example of tunnel collapse engineering,this paper adopts grouting reinforcement,anchor anchor anchor reinforcement arch,shotcrete reinforcement,drainage hole construction and other comprehensive treatment schemes to deal with complex collapse,and provides reference for the treatment of similar engineering accidents.
作者
代成良
王斌元
程朝博
庞旭卿
Dai Chengliang;Wang Binyuan;Cheng Chaobo;Pang Xuqing(Huaneng Tibet Yarlung Zangbo River Hydropower Development Investment Co.,Ltd.,Lhasa 850000,China;Deyang Bollywood Construction Engineering Co.,Ltd.,Deyang 618000,China;China Water Resources and Hydropower Ninth Engineering Bureau Co.,Ltd.,Guiyang 550081,China;Shaanxi Railway Institute,Weinan 714000,China)
出处
《山西建筑》
2021年第19期117-119,共3页
Shanxi Architecture
基金
国家自然科学基金(40772183)
陕西省渭南市科研计划项目(2015KYJ-3-2,ZDYF-JCYJ-221)
陕铁院科研基金项目(KY2019-47)。
关键词
隧道塌方
注浆小导管
超前支护
施工技术
tunnel collapse
grouting small conduit
advanced support
construction technology