摘要
当前,风电塔筒主要采用钢塔筒或者钢混组合塔筒结构形式,超高型混凝土塔筒作为一种新的结构形式,由于其能够有效地提升整机发电量、降低维护成本,得到快速的发展及推广应用。本文结合新疆哈密某风电场工程项目,对超高混凝土塔筒体体内预应力施工及监测技术应用进行了研究,可为类似结构提供参考。
At present,wind power tower drum mainly adopts the structure form of steel tower drum or steel-concrete composite tower drum.As a new structure form,ultra-high concrete tower drum is rapidly developed and applied because it can effectively improve the power generation of the whole machine and reduce the maintenance cost.Combined with a wind power plant project in Hami,Xinjiang,this paper studies the application of prestress construction and monitoring technology in the body of ultra-high concrete tower cylinder,which can provide reference for similar structures.
作者
黄汉斌
简铃方
王波
王雄彪
彭渝舒
王晓琳
HUANG Hanbin;JIAN Lingfang;WANG Bo;WANG Xiongbiao;PENG Yushu;WANG Xiaolin(Liuzhou OVM Machinery Co.,Ltd.,Liuzhou,Guangxi Zhuang Autonomous Region,545006 China)
出处
《科技创新导报》
2021年第17期4-6,共3页
Science and Technology Innovation Herald
关键词
高层建筑
框架结构
无缝钢管
管棚加固
Wind power
Ultra-high concrete tower
Prestressed construction