邕宁水利枢纽一期枯水围堰替代结构及其关键问题

The Alternative Solution and Key Problems of the 1st Stage Cofferdam of Yongning Water Control Project
下载PDF
导出
摘要 为了解决围堰施工进度和料场征地移民进度之间的矛盾,在邕宁水利枢纽工程施工阶段提出了一期枯水围堰设计方案的替代结构型式,并利用施工仿真、技术经济分析方法对围堰型式进行了优选;采用三维数值模拟和物理模型试验方法研究了束窄河床水力特性,结果表明,当纵堰轴线布置在坝体7号至8号闸墩之间时,能够解决施工期通航和围堰防冲问题。研究结果为本工程一期枯水围堰施工提供了重要依据,对于保证工程施工进度起到了决定性作用。 To solve the contradiction between the cofferdam construction progress and the material land requisition and resettlement,the alter⁃native solutions of the designed scheme is proposed during the construction of Yongning water control project 1st stage cofferdam of the dry season,optimized by construction simulation,technical and economic analysis methods.The hydraulic characteristics of the narrowed river⁃bed are investigated by 3D-numerical simulation and physical model test methods.The results show that when the axis is arranged between 7# and 8# gate pier of the dam body,the problem of navigation and scour prevention for the cofferdam can be resolved.The results provide an important basis for the construction of the 1st stage cofferdam of the dry season,thus decisively ensuring the construction progress of this project.
作者 刘德兵 赵彦准 常运超 贺昌海 LIU De-bing;ZHAO Yan-zhun;CHANG Yun-chao;HE Chang-hai(China Railway 20 Bureau Group Corporation,Xi’an 710076,Shaanxi Province,China;State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University,Wuhan 430072,Hubei Province,China)
出处 《中国农村水利水电》 北大核心 2021年第9期167-173,178,共8页 China Rural Water and Hydropower
关键词 围堰 征地移民 施工期通航 防冲 三维数值模拟 物理模型试验 cofferdam land requisition and resettlement navigation during construction scour prevention 3D-numerical simulation physical model test
  • 相关文献

参考文献9

二级参考文献53

共引文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部