单箱多室波形钢腹板组合梁斜拉桥抗弯特性研究 被引量:3

Flexural Behavior of Cable-stay Bridge withMulti-cell Boxed Girders
下载PDF
导出
摘要 本文结合某单箱多室波形钢腹板组合梁斜拉桥的实桥施工,通过塔柱主梁施工过程精细模型的有限元计算,结合实桥施工检测数据,研究施工过程中组合箱梁的抗弯特性。研究结果表明:组合梁斜拉桥施工过程中波形钢腹板纵向应力很小,可不计波形钢腹板的抗弯承载力;施工过程中组合梁顶、底板纵向正应力会出现明显的横桥向不均匀分布现象,顶板尤为严重;施工过程中出现的剪力滞效应,随着施工节段加长趋于平缓。 Based on practical construction of a cable-stay bridge of multi-cell composite boxed girder with corrugated steel web,a FE model of the bridge is proposed,and numerical simulations of construction process of the main tower and main girders are conducted.The onsite monitoring data are used to validate the analytic model,and flexural behavior of composite girders during the construction process is investigated.It is illustrated that the induced longitudinal stresses of the corrugated steel web during each construction stage of the cable-stay bridge are very small,and have negligible effect on the flexural bearing capacity of the steel web.During the construction process of the bridge,longitudinal normal stresses in the top and bottom concrete flanges have apparent non uniform distributed pattern,especially in the top flange.This shear lag phenomenon in distribution of normal stress,however becomes gentle as advance of the construction stages.
作者 顾萍 裴辉腾 鲁凡 王兵 GU Ping;PEI Huiteng;LU Fan;WANG Bing(Tongji University,Shanghai 200092,China;Shanghai Urban Construction Municipal Engineering(Group)Co.,Ltd.,Shanghai 200065,China)
出处 《结构工程师》 2021年第4期167-173,共7页 Structural Engineers
基金 国家自然科学基金资助项目(51578407)。
关键词 单箱多室波形钢腹板组合箱梁 施工过程 监测 正应力 剪力滞 multi-cell composite boxed girder with corrugated steel web construction process monitoring normal stress shear lag
  • 相关文献

参考文献7

二级参考文献35

共引文献259

同被引文献27

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部