摘要
对建设新能源电站高电压穿越试验平台进行原理分析,提出适用于青海高海拔地区新能源及储能电站高电压穿越平台的设计应用方法,在此基础上对青海电力公司高电压穿越试验平台建成投运进行系统描述,可为新能源储能联合发电系统高电压穿越检测提供参考。
The principle analysis of the high voltage ride through test platform for the construction of new energy power stations is carried out,and a design and application method suitable for the high voltage ride through platform of new energy and energy storage power stations in Qinghai high altitude areas is proposed.On this basis,the high voltage ride through test of Qinghai Electric Power Company The platform is completed and put into operation for system description,which can provide a reference for the high voltage ride through detection of the new energy storage combined power generation system.
作者
李东升
杨军
闫涵
杨凯璇
LI Dongsheng;YANG Jun;YAN Han;YANG Kaixuan
出处
《青海电力》
2021年第3期39-43,共5页
Qinghai Electric Power
关键词
新能源电站
高电压穿越
试验平台
应用设计
new energy power station
high voltage ride through
test platform
application design