摘要
文章以周宁抽水蓄能电站为例,进行了其引水隧洞充排水试验方案设计、试验过程及试验结果的分析探讨,结果表明,充排水试验是水电站引水隧洞工程施工质量检测及查找引水系统可能存在安全隐患的主要方式,在抽水蓄能电站投产发电前,其引水发电系统充排水试验必不可少。试验结果显示,该抽水蓄能电站引水系统设计合理,施工质量良好,结构性能可靠,且所采取的充排水试验程序合理,措施得当,充排水试验取得了成功。
Taking Zhouning pumped-storage power station as an example,the paper analyzes and discusses the design of diversion tunnel charging and drainage test scheme and test results.The results show that the filling and drainage test is the main way to detect the construction quality of diversion tunnel and find out the potential safety hazards of diversion system,and the charging and drainage test of diversion system is essential before the pumped storage power station is put into operation.The test results show that the water diversion system of the pumped storage power station is reasonable in design,good in construction quality,reliable in structure performance,reasonable in charge and drainage test procedure and appropriate measures,and the water filling and drainage test is successful.
作者
朱正龙
王晓
ZHU Zheng-long;WANG Xiao(Jiangxi Provincial Ganyu Engineering Construction Limited Company,Nanchang 330001,China)
出处
《黑龙江水利科技》
2021年第10期6-8,129,共4页
Heilongjiang Hydraulic Science and Technology
关键词
抽水蓄能电站
引水系统
充排水试验
pumped-storage power station
water diversion system
water filling and draining test