摘要
滇中引水工程狮子山隧洞3号支洞主洞控制段上游侧多次发生突水突泥事件,其两次突水突泥的总量合计8200m 3。为保证安全、平稳地通过突涌段落,现场采用超前预灌浆双液注浆施工技术,在增大经济和社会效益的同时满足了突涌段安全开挖支护的施工要求。文章研究结果可为类似工程的突水突泥控制技术提供借鉴参考。
Water and mud inrushare generatedfor many times at the upstream side of the control section of the main tunnel of No.3 branch tunnel of ShizishanTunnel in Central Yunnan Water Diversion Project.The total amount of twice water and mud inrushis 8200m 3.The construction technology of pre-grouting and double-liquid grouting is adopted in the site in order to ensure the safe and stable passage through the inrush section,thereby not only increasing the economic and social benefits,but also meeting the construction requirements of safe excavation and support in the inrush section.The research results of the paper can provide reference for the control technology of water and mud inrush based on engineering and similar engineering.
作者
刘浩
LIU Hao(China Railway 18th Bureau Group No.2 Engineering Co.,Ltd.,Fengrun 064000,China)
出处
《中国水能及电气化》
2021年第9期47-51,共5页
China Water Power & Electrification
关键词
滇中引水工程
狮子山隧洞
突水突泥
双液注浆
Central Yunnan Water Diversion Project
Shizishan Tunnel
water and mud inrush
double liquid grouting