成庄矿15号煤层坚硬难垮顶板定向水力压裂技术研究 被引量:8

Study on directional hydraulic fracturing technology for hard and hard roof in thick coal seam
下载PDF
导出
摘要 为了有效解决成庄矿15号煤首采面坚硬顶板垮落困难的问题,提出定向水力压裂弱化顶板的施工方案。通过现场生产地质条件调研,确定最优的压裂钻孔布置参数。后期钻孔窥视结果表明:通过定向水力压裂施工有效弱化15号煤上覆坚硬顶板,正常情况下能保证岩层的稳定下,随着工作面回采煤层上覆坚硬岩层可实现分层垮落,保证工作面的安全回采。 In order to effectively solve the problem of hard roof caving in the first mining face of No.15 coal seam in Chengzhuang Coal Mine,the construction scheme of weakening roof by directional hydraulic fracturing is proposed.Through the investigation of the geological conditions in the field,the optimal parameters of fracturing borehole layout are determined.The late drilling peep results show that:through directional hydraulic fracturing construction effectively weaken the hard roof of No.15 coal seam,under normal circumstances,it can ensure the stability of the rock stratum,and with the mining face mining,the overlying hard rock layer of the coal seam can realize layered collapse,and ensure the safe mining of the working face.
作者 李浩男 LI Haonan(Jinneng holding Chengzhuang Mine of coal industry group,Jincheng048000,China)
出处 《煤矿现代化》 2021年第5期21-22,25,共3页 Coal Mine Modernization
关键词 厚煤层 坚硬顶板 钻孔 水力压裂 Thick coal seam hard Hard to collapse hydraulic fracturing
  • 相关文献

参考文献7

二级参考文献56

共引文献191

同被引文献104

引证文献8

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部