摘要
白鹤滩水电站位于金沙江下游四川省宁南县和云南省巧家县境内,开发任务以发电为主,兼顾防洪,并有拦沙、发展库区航运和改善下游通航条件等综合利用效益,是西电东送骨干电源点之一。论文对白鹤滩水电站大坝砂石加工系统工程整体规划和工程设计进行了分析和讨论,希望能为水电站工程规划和设计提供有益的参考依据。
Baihetan Hydropower Station is located in Ningnan County,Sichuan Province and Qiaojia County,Yunnan Province in the lower reaches of Jinsha River.Its development task is mainly to generate electricity,taking into account flood control,and has comprehensive utilization benefits such as blocking sand,developing shipping in the reservoir area and improving navigation conditions in the lower reaches.It is one ofthe backbone power supply points for power transmission from west to east.This paper analyzes and discusses the overall planning and engineering design of the dam sand and gravel processing system of Baihetan Hydropower Station,hoping to provide reference for the planning and design of hydropower station.
作者
莫让华
MO Rang-hua(Sichuan Ertan International Engineering Consulting Co.Ltd.,Chengdu 611130,China)
出处
《工程建设与设计》
2021年第18期72-74,共3页
Construction & Design for Engineering
关键词
白鹤滩水电站
砂石
规划
设计
Baihetan Hydropower Station
sand and gravel
planning
design