摘要
西安咸阳机场三期扩建规模大、地基处理和地质条件复杂,对机场建设期和运营期地基沉降变形控制要求高。利用智慧跑道建设契机,机场针对湿陷性黄土、填挖交界、下穿工程、新老交界等工程难点,采用场道地基沉降变形监测新技术,构建了建设-运营一体化地基沉降智能监测设计与优化方案,为控制机场场道沉降变形、提升建设、运营安全性提供技术保障。
Xi’an Xianyang International Airport’s Phase Ⅲ expan sion is large in scale,complicated in foundation tr eatment and geological conditions,and has a high requirement for foundation settlement deformation control during the construction and oper ation periods.Airport takes the opportunity of smart runway construction to adopts the multi-sour ce technology of foundation settlement deformation monitoring and builds an integrated construction-operation foundation settlement monitoring design and optimization plan for engineering difficulties such as collapsible loess,fill-dig junction,under-passing projects,old and new junction,etc..It provides technical guarantee for controlling airport field settlement deformation and improving construction and oper ation safety.
作者
程峰
CHENG Feng(China West Airport Group,Xi'an 710065,China)
出处
《工程建设与设计》
2021年第18期105-108,共4页
Construction & Design for Engineering
关键词
智慧跑道
地基沉降
智能监测
设计优化
smart runway
foundation settlement
intelligent monitoring
design and optimization