摘要
为解决新2号高炉调车场交叉渡线影响运输和行车安全问题,在铁水鱼雷罐车走行区域实施铁路道岔混凝土轨枕改造,提高了铁路道岔的质量;同时做好铁路道岔的日常保养和补修,实行精细作业,减少了日常维护投入,保证行车安全。
The crossing lines influence the transportation and driving safety in the new No.2 blast furnace switchyard.Make a modification on the concrete sleeper of railway turnout in the traveling area of torpedo cars in order to solve this problem.The quality of railway turnout is improved.Good daily maintenance and repair for turnouts are carried out at the same time.The fine work is implemented,and the daily maintenance input is reduced.Driving safety is ensured.