摘要
反应堆冷却剂泵是核电厂的关键设备。本文通过K2项目和其他同类项目经验反馈的整理和吸收,在装配工艺流程的优化,质量管理和风险管控上探索K3项目反应堆冷却剂泵装配进度控制的方法,大幅提升了K3项目进度控制水平。
A reactor coolant pump is the key equipment of nuclear power plant.Through sorting out and absorbing the experience feedback of the K2 project and other similar projects,this paper explored the method of controlling the assembly schedule of the reactor coolant pump of K3 project in terms of optimization of assembly process,quality management and risk control,and greatly improved the schedule control level of the K3 project.
作者
夏亮
朱伟
任兴龙
XIA Liang;ZHU Wei;REN Xing-long(China Zhongyuan Engineering Corp.,Beijing 100044,China)
出处
《中国核电》
2021年第5期705-710,共6页
China Nuclear Power
关键词
反应堆冷却剂泵
现场装配
进度控制
reactor coolant pump
on-site assembly
schedule control