摘要 本文以某核电厂排水口为研究基础,通过物理模型试验对消能坎、消力墩、消力池、护底混凝土板等多种消能和防冲刷设施的不同组合、不同布置形式及不同的尺度进行优化分析研究,从而形成核电厂排水口消能设施方案。通过试验可知,在排水口内设置消力墩、提高尾坎高度,使得水流在排水口内尽量充分消能,能够达到分流、扩散、消能的效果,有效防止排水口附近区域的冲刷。试验成果可为类似核电厂或火电厂等排水口防冲刷工程提供参考。 Based on the outfall of one nuclear power plant,physical model tests are carried out to analyze the effect of different combinations,layout forms and scales of such energy dissipation and anti-scouring facilities as energy dissipation curb,block,basin and concrete bottom-protective slab,which leads to final plan of energy dissipation facilities at outfall of the nuclear power plant.The test results show that the arrangement of baffle block and the increased height of energy dissipation curb dissipate energy of water flow before the outfall as much as possible,which achieves split-flow,diffusion and energy dissipation,and effectively prevents the area near the outfall from scouring.The research can provide a reference for similar anti-scouring works at the outfalls of nuclear power plants or thermal power plants.
作者 王秉昌 王书昇 张俊 夏悟民 Wang Bingchang;Wang Shusheng;Zhang Jun;Xia Wumin(CCCC-FHDI Engineering Co.,Ltd.,Guangzhou,Guangdong,510230,China;CNNP Xiapu Nuclear Power Co.,Ltd.,Ningde Fujian 355199,China)
出处 《港工技术》 2021年第5期58-63,共6页 Port Engineering Technology
关键词 核电厂排水口 消能和防冲刷措施 物模试验 平面优化 outfall of nuclear power plant energy dissipation and anti-scouring measures physical mode test plane optimization
  • 相关文献

参考文献8

二级参考文献48

共引文献50

同被引文献18

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部