PPP项目风险识别与分担研究

Research on PPP Project Risk Identification and Sharing
下载PDF
导出
摘要 PPP项目有周期长、投资大、结构复杂和风险高等特点,由于对项目风险的识别不足、风险归属划分不明确出现争议,增加项目成本、降低建造效率,甚至项目失败。本文首先通过文献阅读识别PPP项目的22个风险,接着对22个具体风险分析其合理分担方,随后用层次权重分析法得出政府信用差、征用/国有化、政策变更、政府决策失误和私营企业能力不足在22个风险因素中权重排名前五,最后对公共部门与私营企业给出相应建议。 PPP projects have the characteristics of long cycle,large investment,complex structure and high risk.Due to insufficient identification of project risks and unclear attribution of risk,disputes have arisen,increasing project costs,reducing construction efficiency,and even project failure.This article first identifies 22 risks of the PPP project through literature reading,and then analyzes the reasonable share of 22 specific risks,and then uses the hierarchical weight analysis method to obtain government credit difference,expropriation/nationalization,policy changes,government decision-making errors,and private ownership.Insufficiency of corporate capabilities ranks in the top five weighted among 22 risk factors,and finally gives corresponding recommendations to the public sector and private companies.
作者 刘祖容 叶明珠 龙湖荣 LIU Zu-rong;YE Ming-zhu;LONG Hu-rong(School of Civil Engineering and Architecture,Guangxi University,Nanning 530004,China;Key Laboratory of Engineering Disaster Prevention and Structural Safety of Ministry of Education,University,Nanning 530004,China;Guangxi Key Laboratory of Disaster Prevention and Mitigation Safety,Nanning 530004,China)
出处 《价值工程》 2021年第30期54-56,共3页 Value Engineering
关键词 PPP 风险识别 风险分担 层次权重分析法 PPP risk identification risk sharing hierarchical weight analysis
  • 相关文献

参考文献3

二级参考文献26

  • 1罗春晖.基础设施民间投资项目中的风险分担研究[J].现代管理科学,2001(2):28-29. 被引量:35
  • 2刘新平,王守清.试论PPP项目的风险分配原则和框架[J].建筑经济,2006,27(2):59-63. 被引量:264
  • 3Clifford Chance法律公司 龚辉宏(译).项目融资[M].北京:华夏出版社,1997..
  • 4Tiong RLK, Alum J. Final negotiation in competitive BOT tender[J]. Journal of Construction Engineering and Management, 1997, 123(1): 6-10
  • 5Lam K C, Wang D, Lee P T K, et al. Modeling risk allocation decision in construction contracts [J]. International Journal of Project Management, 2007, 25 (5): 485-493
  • 6Rutgers J A, Haley H D. Project risks and risk allocation [J]. Cost Engineering, 1996, 38(9): 27-30
  • 7Groupe Eurotunnel. Our History lOLl. http: //www. eurotunnel.com/ukcP3Main/ukcCorporate/ukcAboutUs/ukc OurHistory/ukpHistory.htm
  • 8Francis W A. The channel tunnel: a case study [R]. Washington, D C: National Defense University, 1993
  • 9Kirkland C J. The channel tunnel: lessons learned[J]. Tunneling and Underground Space Technology, 1995, 10(1): 5-6
  • 10Smith A J. Privatized Infrastructure: the role of government [M]. New York: Thomas Publishing Company, 1999

共引文献290

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部