摘要 研究了顶吹转炉双渣法冶炼中高磷铁水的工艺方案,并进行了工业试验。通过合理搭配铁矿石、废钢和氧气比例,抑制熔池温度,分析了冶炼过程需要控制的关键因素。结果表明:在铁水磷质量分数为0.12%~0.15%条件下,半钢渣碱度控制在2.0~2.3,TFe质量分数控制在15%~18%;终点渣碱度控制在3.0~3.5,TFe质量分数控制在15%~18%,半钢倒渣量40%~60%,可以使转炉终点磷质量分数控制在0.008%。 The process scheme of dual slag smelting with middle and high phosphorus hot metal in the top blown converter was studied,and industrial test was carried out.The temperature of molten pool could be restrained by controlling the reasonable proportion of iron ore,scrap steel and oxygen.Some key factors of operating system during the blowing process were analyzed through the industrial experiments.The results showed that,when phosphorus mass fraction in the hot metal was 0.12%to 0.15%,basicity and w(TFe)of half steel slag controlled within 2.0 to 2.3 and 15%to 18%respectively;basicity and w(TFe)of slag at end point controlled within 3.0 to 3.5 and 15%to 18%respectively;deslaging quantity of semi steel was within 40%to 60%,and the phosphorus mass fraction at end point of converter could be controlled at 0.008%.
作者 丁宁 孟义春 李宁 韩学义 王勇 姜卓豪 DING Ning;MENG Yichun;LI Ning;HAN Xueyi;WANG Yong;JIANG Zhuohao(Shougang Research Institute of Technology,Beijing 100043,China;Steel Making Plant,Shougang Changzhi Iron and Steel Limited Company,Changzhi 046031 Xhina)
出处 《炼钢》 CAS 北大核心 2021年第5期6-11,28,共7页 Steelmaking
关键词 中高磷铁水 双渣 深脱磷 顶吹转炉 middle and high phosphorus hot metal double slag deep dephosphorization top-blowing converter
  • 相关文献

参考文献9

二级参考文献82

  • 1吴伟,邹宗树,郭振和,李永祥.复吹转炉钢-渣间容量传质系数的研究[J].安徽工业大学学报(自然科学版),2003,20(z1):25-28. 被引量:1
  • 2周有预,喻承欢,徐静波,冯军.转炉铁水脱磷预处理直炼工艺试验研究[J].炼钢,2004,20(5):40-43. 被引量:11
  • 3康复,陆志新,蒋晓放,钟志敏.宝钢BRP技术的研究与开发[J].钢铁,2005,40(3):25-28. 被引量:35
  • 4王金平,吴健鹏,李小明,徐永清.转炉高碳低磷钢工艺研究与应用[J].炼钢,2007,23(2):7-10. 被引量:14
  • 5Kitamura S, Yonezawa K, Ogawa Y, et al. Improvement of Reaction Efficiency in Hot Metal Dephosphorization [J]. Ironmaking and Steclmaking, 2002, 29(2) : 121.
  • 6Ogawa Y, Yano M, Kitamura S, et al. Development of Continuous Dephosphorization and Decarboniztion Process Using BOF[J].Tetsu-To-Hagane, 2001, 87(1) :21.
  • 7Torii K. Improvement of Dephosphorization Capacity in SRP [J].CAMP-ISIJ, 1998,(11) :142.
  • 8Tanaka S. Development of Steelmaking Process With Minimum Slag Generation in No. 3 SMS, Fukuyama Works[J]. CAMP-ISIJ, 1997, ( 1 1 ) : 144.
  • 9Song H. Hot Metal Pretreatment in a Converter[J]. CAMPISIJ, 1997,(10) :781.
  • 10Wakamastu S. Dephosphorization at Hot Metal Pretreatment in a BOF Vessel[J]. CAMP-ISIJ, 1996,(9):864.

共引文献134

同被引文献106

引证文献5

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部