摘要
本文重点讨论了风电场升压站的电气安装、调试工艺、安全施工及监管措施。在风电场建设中,升压站是展开工作的核心部分,其作用相当于阀门的功能,经过升压变电站可将电厂输出的电进行升压传送。升压站系统主要包括主变压器、高压开关柜、低压配电柜、母线、接地保护、继电保护及控制系统等。在安装和调试的具体实践中,要强化施工质量、安全监管及试运行工作,以确保各设备能够安全、稳定运行,并要注重检查各设备的产品质量。
This paper focuses on the electrical installation,debugging process,safety construction and supervision measures of wind farm booster substation.In the construction of wind farm,the booster substation is the core part of the work.Its function is equivalent to the function of valve.The power output from the power plant can be boosted and transmitted through the booster substation.The booster substation system mainly includes main transformer,high-voltage switchgear,low-voltage distribution cabinet,bus,grounding protection,relay protection and control system.In the specific practice of installation and commissioning,the construction quality,safety supervision and trial operation shall be strengthened to ensure the safe and stable operation of all equipment,and the product quality of all equipment shall be inspected.
作者
王宁
WANG Ning(Offshore Oil Engineering(Qingdao)Co.,Ltd.,Qingdao 266520,Shandong,China)
出处
《电气传动自动化》
2021年第4期61-64,共4页
Electric Drive Automation
关键词
风电场
升压站
安装
调试
研究
wind farm
booster substation
installation
debugging
research