摘要 立井井筒施工接近采空区时,易造成采空区积水突水、瓦斯涌出等事故,严重影响施工安全,同时治理困难。塔山煤矿四盘区回风立井施工中,为解决上述问题,通过对采空区进行实测勘探,结合收集整理的该区地质资料,确定了井筒通过采空区的范围和隐蔽灾害情况。井筒通过采空区施工时,采用灌注结合、井壁加固等技术,对采空区进行治理,取得预期效果。 When the mine shaft construction closed to the goaf,a standing water inrush,gas emission and other accident would be easily caused in the goaf,would seriously affect the safe construction and would be difficult to be controlled.During the construction of the mine air return shaft in No.4 Block of Tashan Mine,in order to solve the above problems,a field survey and exploration was conducted on the goaf and the geological information of the block was collected and prepared.Thus the scale of the mine shaft passed through the goaf and the potential disaster condition were determined.When the mine shaft construction passed through the goaf,the pouring and grouting combination,mine shaft reinforcement and other technology were applied to control the goaf.The expected results were obtained.
作者 刘彦杰 LIU Yanjie(No.49 Engineering Division,China Coal First Construction Company Limited,Handan 056003,China)
出处 《建井技术》 2021年第5期10-15,共6页 Mine Construction Technology
关键词 煤矿立井 采空区 综合物理勘探法 灌注结合 井筒加固 mine shaft goaf integrated geophysical exploration pouring and grouting combination mine shaft reinforcement
  • 相关文献

参考文献7

二级参考文献28

共引文献37

同被引文献12

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部