摘要
为了有效解决太平排涝泵站施工的重点和难点问题,通过利用BIM技术,建立了泵站模型,将流道模型建立、深化设计、二维码技术、施工方案模拟与优化、无人机进度实施把控、无人机倾斜摄影技术、土方结算三维算量复核等方面深入运用BIM技术进行辅助管理,探索BIM平台应用,提高信息化管理水平,可为类似工程提供借鉴。
In order to effectively solve the key and difficult problems in the construction of Taiping Drainage Pumping Station,the pumping station model was established by using BIM technology,and the runner model was established,deepened design,two-dimensional code technology,construction plan simulation and optimization,and UAV schedule implementation In-depth use of BIM technology for auxiliary management in control,drone tilt photography technology,and three-dimensional calculation of earthwork settlement,and explore the application of BIM platform to improve the level of information management,which can provide a reference for similar projects.
作者
范浩威
卢杰
马定球
FAN Haowei;LU Jie;MA Dingqiu(Guangdong No.3 Water Conservancy and Hydro-Electric Engineering Board Co., Ltd., Dongguan 523710, China)
出处
《广东水利水电》
2021年第11期96-100,共5页
Guangdong Water Resources and Hydropower
关键词
BIM技术
施工进度
施工模拟
项目管理
BIM technology
construction schedule
construction simulation
project management