摘要
目前,工程量清单计价已成为国有投资项目招标采取的主要计价方式。首先,介绍了国有投资项目工程量清单与招标控制价编制的基本流程,然后,分析了编制过程中存在的常见问题,最后,提出了相应的质量控制措施,以期为相关从业人员提供参考。
Currently,the valuation of the bill of quantities has become the main valuation method adopted in the bidding of state-owned investment projects.Firstly introduces the basic process of the engineering quantity list and bidding control price of state-owned investment projects,then analyzes the common problems in the compiling process,and finally puts forward the corresponding quality control measures in order to provide reference for relevant practitioners.
作者
任杰
REN Jie(CCB Engineering Consulting Co.,Ltd.Anhui Branch,Hefei 230001,China)
出处
《工程经济》
2021年第10期27-30,共4页
ENGINEERING ECONOMY
关键词
国有投资项目
清单控制价
编制流程
常见问题
控制措施
state-owned investment projects
engineering quantity list and bidding control price
preparation process
common problems
control measures