高低基础沉箱间隔安装施工应用

Application of interval installation of caissons with high and low foundations
下载PDF
导出
摘要 通过对大连湾海底隧道建设工程干坞子项工程-防波堤工程高低基础沉箱间隔安装施工,明确了各工序施工所采取的相应技术质量控制措施及合理的施工顺序。结果表明:通过采取相应的技术质量控制措施及合理安排各工序的施工顺序,西防波堤高低基础沉箱一次性安装成功。 Through the construction of interval installation of caissons of high and low foundations in dry dock sub-project of Dalian Bay subsea tunnel project,the corresponding technical quality control measures and reasonable construction sequence adopted in each construction procedure were defined.The results show that the caissons of the high and low foundations of the west breakwater have been successfully installed at one time by adopting the corresponding technical quality control measures and arranging the construction sequence reasonably.
作者 林玉葵 LIN Yu-kui(No.3 Engineering Co.,Ltd.of CCCC First Harbor Engineering Co.,Ltd.,Dalian,Liaoning 116083,China;Tianjin Key Laboratory of Construction,Operation and Maintenance Technologies for Underwater Tunnels,Tianjin 300461,China)
出处 《中国港湾建设》 2021年第11期58-60,68,共4页 China Harbour Engineering
关键词 沉箱安装 高低基础 间隔安装 质量控制 施工顺序 caisson installation high and low foundations interval installation quality control construction sequence
  • 相关文献

参考文献6

二级参考文献14

共引文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部