级联电池储能系统能实现6~35 kV电压等级直接并网,有利于实现电池储能的大容量化,在电网中有良好的应用前景。但大容量高压级联电池储能系统体积大,分布参数的影响突出。深入分析分布电容对电池管理系统测量电路和通信电路的影响机理,并提出消除分布电容影响的方法和措施。
Cascaded battery energy storage system is suitable for 6~35 kV voltage level direct grid connection,which is conducive to the large capacity of battery energy storage,and has a good application prospect in power grid.However,the large-capacity and high-voltage cascade battery energy storage system is large in size,and the influence of the distribution parameters is prominent.In this paper,the influence mechanism of distributed capacitance on the measurement circuit and communication circuit of battery management system is analyzed,and the methodsand measures to eliminate the influence of distributed capacitance are put forward.
作者
陈满
李勇琦
李毓烜
凌志斌
CHEN Man;LI Yongqi;LI Yuxuan;LING Zhibin(Technology Center of CSG Power Generation Company,Guangzhou 510630,China;CSG Advanced Energy Storage Technology Joint Laboratory,Guangzhou 510630,China;Key Laboratory of Control of Power Transmission and Conversion,Shanghai Jiao Tong University,Shanghai 200240,China)
出处
《电工技术》
2021年第20期52-55,共4页
Electric Engineering
基金
国家自然科学基金面上项目(编号51777125)
南方电网重点项目(编号0200002020030304JS0031)。
关键词
级联电池储能系统
电池管理
分布电容
共模干扰
cascaded battery energy storage system
battery management
distributed capacitance
common mode interference