摘要
生态电站凭借着经济与环境的共同优势,成为近年来水电站发展的热点。恰木萨水电站工程的施工安装中方案设计生态电站与主电站间距离约12 km,生态电站设计打捆送出至主电站后接入220 kV电网,但是由于生态电站先于主电站机组安装发电,主电站变电站尚未安装调试,针对上述施工问题,阐述了根据当地电网情况将生态电站电能临时送出附近农网,待主电站变电站投运后再行接入的解决方案,为同类工程提供参考依据。
With the common advantage of the development of hydropower station in recent years.In the construction and installation of Chamussa Hydropower Station,the ecological power station is about 12 km,to the main power station and access 220 kV power grid before the main power station unit and commissioning.However,this paper describes the solution of temporarily sending the ecological power station from the nearby agricultural power grid according to the local power grid,which provides reference basis for similar projects.
出处
《电力系统装备》
2021年第21期92-93,共2页
Electric Power System Equipment
关键词
水电站
送出工程
并网运行
主接线
hydropower station
delivery project
grid-connection operation
main connection