资源受限的飞机总装脉动生产线节拍转换调度建模 被引量:1

Modeling of Resource Constrained Project Takt Transition Scheduling Problem for Aircraft Pulsating Assembly Line
下载PDF
导出
摘要 以飞机总装脉动生产线节拍转换过程为实际生产背景,提出基于项目拆分的资源受限项目节拍转换调度问题,并建立了以最小化转换期时长为目标函数的数学模型。根据项目节拍转换调度问题的特点,采用双层迭代算法进行求解。结果表明:该算法有效缩短生产线节拍转换时间,对不同项目组合的优化程度为1.1%~23.4%。 A resource constrained project takt transition scheduling problem based on project splitting was proposed under the background of aircraft pulsating assembly line takt transition process,and a mathematical model was established with the objective function of minimizing total transition time.According to the feature of the problem,a two-level iterative algorithm was developed.It is shown that the algorithm can decrease the transition time effectively and the degree of optimization for different project portfolios is 1.1%~23.4%.
作者 陆志强 王浩宇 LU Zhiqiang;WANG Haoyu(School of Mechanical Engineering,Tongji University,Shanghai 201804,China)
出处 《同济大学学报(自然科学版)》 EI CAS CSCD 北大核心 2021年第12期1761-1770,共10页 Journal of Tongji University:Natural Science
基金 国家自然科学基金(61473211)。
关键词 多项目调度 项目拆分 作业划分 飞机总装脉动生产线 禁忌搜索 multi-project scheduling project splitting job allocation aircraft pulsating assembly line Tabu search