摘要
文章以某28700载重吨散货船加装水泥装卸设备并改装为26500载重吨自卸式水泥运输船项目为例,选取改装过程中货舱区改造、高效卸货设计、水泥螺杆泵和气流床安装等关键工程设计进行了介绍和探讨,为类似自卸式水泥船改装设计提供技术支撑。
Taking one conversion project from 28700 DWT bulk carrier to 26500 DWT self-discharging cement carrier as sample,the key project design work including structure conversion design in cargo hold area,efficient unloading design,cement screw pump installation and fluidizing panel installation are introduced and discussed.The content in this article could provide technical reference and support for the other similar conversion project.
作者
赵锐
ZHAO Rui(COSCO Shanghai Shipyard Co.,Ltd.,Shanghai 200231,China)
出处
《船舶标准化工程师》
2021年第6期38-41,58,共5页
Ship Standardization Engineer
关键词
自卸式水泥运输船
高效卸货
水泥螺杆泵
气流床
self-discharging cement carrier
efficient unloading
cement screw pump
fluidizing panel