摘要
随着目前印度市场对水泥船需求量的增加,出于经济性考虑,将旧散货船改装成自卸式水泥船的项目应运而生。文章以“DARYA SHAAN”自卸式水泥船改装项目为例,分析在报价、图纸设计和建造阶段所涉及的电气设计内容。研究成果可为类似改装项目的设计人员在设计流程和项目把控方面提供一定指导。
With the increasing demand for Cement Carrier in the India market,for economic consideration,the project of converting old bulk carrier into cement carrier emerged as the times require.Taking the refitting project of'DARYA SHAAN'self-discharging cement carrier as an example,the electrical design contents involved in the quotation,drawing design and construction stages are analyzed.The research results can provide some guidance for designers of similar refitting projects in the design process and project control.
作者
陈龙
CHEN Long(COSCO Shanghai Shipyard Co.,Ltd.,Shanghai 200231,China)
出处
《船舶标准化工程师》
2021年第6期74-77,88,共5页
Ship Standardization Engineer
关键词
自卸式水泥船
改装
电气设计
self-discharging cement carrier
refit
electrical design