摘要
某铅锌选矿厂存在钢球尺寸单一、新生-0.074 mm含量偏低、过磨现象严重等问题。在生产流程中选取代表性矿样测定原矿力学性质和粒度组成,结合理论计算和试验结果为生产提供合理的钢球配比。研究结果表明:该矿石韧性和脆性偏高,通过破碎函数、段氏球径半理论公式和对比试验结果,采用?准80∶?准60∶?准40∶?准30=25∶35∶20∶20的推荐方案较现场方案在中间可选级别(0.01~0.15)mm产率提高6.06个百分点,易选级别(0.028~0.074)mm产率提高4.39个百分点,-0.074 mm含量提高8.65个百分点,磨矿效果优化明显。
One lead-zinc dressing plant has the following serious problems,such as single size of steel ball,low content of newly produced-0.074 mm product and serious over-grinding.In the production process,we select the representative ore sample to determine its mechanical property and granularity composition,and combining with the theoretic calculation and test results,the reasonable steel ball proportion can be provided.The research results show:the ore has high toughness and fragility,we adopted the breakage function,Duan's sphere diameter semi-theoretical formula and contrast test's results,and we also adopted the recommended scheme thatΦ80∶Φ60∶Φ40∶Φ30=25∶35∶20∶20,therefore the yield of middle optional level(0.01~0.15)mm was increased by 6.06%,the yield of easy-to-select level(0.028~0.074)mm was increased by 4.39%,the content with-0.074 mm mesh was increased by 8.65%,the ore grinding results was optimized obviously.
作者
王明飞
杨芳
WANG Ming-fei;YANG Fang(Yunnan Chihong Zn&Ge Co.,Ltd.,Qujing,Yunnan 655000,China;Kunming Metallurgical Research Institute Co.,Ltd.,Kunming,Yunnan 650031,China;The Key Lab of New Technology for Mineral Processing and Metallurgy of Yunnan Province,Kunming,Yunnan 650031,China;State Key Laboratory of Pressure Hydrometallurgical Technology of Associated NonferrousMetal Resources,Kunming,Yunnan 650031,China)
出处
《云南冶金》
2021年第6期43-46,共4页
Yunnan Metallurgy
关键词
铅锌矿
球磨机
钢球
介质配比
粒度组成
磨矿优化
lead-zinc ore
ball mill
steel ball
media ratio
granularity composition