摘要 堆芯中子通量测量系统大修期间需要在堆芯仪表间进行诸多检修操作,环境剂量偏高以及严重的松散污染增加了检修工作人员的吸收剂量以及沾污风险通过对堆芯仪表间辐射热点设备电动阀、止回阀的辐射剂量降低研究,分析电动阀的工作原理,确保清洗后的设备性能满足要求的前提下,实现了电动阀、止回阀辐射剂量的有效降低,同时对电动阀、止回阀的承压性能进行有效验证,此外也为核电厂其他热点设备的辐射剂量降低提供了一定参考。 During the overhaul of the core neutron flux measurement system,many maintenance operations are required in the core instrument room.The high environmental dose and serious loose pollution increase the absorbed dose of the maintenance staff and the risk of contamination.In this paper,the radiation dose reduction of the electric valve and check valve of the radiation hot spot equipment between the core instruments and the working principle of the electric valve are analyzed.The radiation dose of the electric valve and the check valve is effectively reduced,which based on the effective verification of pressure-bearing performance of the valve.At the same time,this article also provides a certain reference for the radiation dose reduction of other hotspot equipment in nuclear power plants.
作者 唐龙 高秉瀚 张建兵 祝伟健 Tang Long;Gao Binghan;Zhang Jianbing;Zhu Weijian(CNNP Nuclear Power Operations Management Co.,Ltd.,Zhejiang,Haiyan,314300,China)
出处 《仪器仪表用户》 2022年第2期74-77,59,共5页 Instrumentation
关键词 堆芯中子通量测量 辐射剂量降低 电动阀 止回阀 热点设备 core neutron flux measurement radiation dose reduction electric valve check valve hot spot equipment
  • 相关文献

参考文献8

二级参考文献26

  • 1上海核工程设计院.C2工程堆芯中子注量率测量系统技术规格书[Z].上海:上海核工程设计院,2005.
  • 2Eric Freeman,深入浅出设计模式[M].美国:Oreilly & Associates Inc,2008.
  • 3GB/T 12232-2005,通用阀门法兰连接铁闸阀[S].
  • 4ASME QME-1-2002, Qualification of Active Mechanical Equipment Used in Nuclear Power Plants[S].
  • 5ASME Boiler and Pressure Vessel Code, Section III, Rules for Construction of Nuclear Power Plant Components, Divis- ion 1, Subsection NC[S].
  • 6JTG D62-2004.公路钢筋混凝土及预应力混凝土桥涵设计规范[S]..2004
  • 7GB 50010-2002.混凝土结构设计规范[S]..2002
  • 8.Design response spectra for seismic design of nuclear power plants[]..1973
  • 9EUROCODE 2:DESIGN OF CONCRETESTRUCTURES. EN 1992-1-1 . 2008
  • 10李军业,张宗列,乐秀辉.核电阀门的试验鉴定[J].阀门,2009(4):17-20. 被引量:12

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部