深水铺管船铺管区通风系统设计

Design of Ventilation System in Pipe Laying Area of Deepwater Pipe Laying Vessel
下载PDF
导出
摘要 以某在建深水(3000 m)铺管船为例,分析各铺管作业区域的工作环境条件。根据工作区域的设备布置和工序操作,设计不同的通风系统气流组织方案并给出具体技术措施,以期改善铺管作业人员的工作环境。研究成果可为类似铺管船通风系统的设计提供一定参考。 Taking a deepwater(3000 m)pipe laying vessel under construction as an example,the working environment conditions of each pipe laying operation area are analyzed.According to the equipment layout and process operation in the working area,the different ventilation system airflow organization schemes are designed and the specific technical measures are given,in order to improve the working environment of pipe laying operators.The research results can provide certain references for the design of the ventilation system of similar pipe laying ships.
作者 张译元 ZHANG Yiyuan(Shanghai Zhenhua Heavy Industries Co.,Ltd.,Shanghai 200125,China)
出处 《船舶标准化工程师》 2022年第1期47-51,56,共6页 Ship Standardization Engineer
关键词 铺管船 通风系统 焊接通风 除尘 气流组织 pipe laying vessel ventilation system welding ventilation dust removal air organization
  • 相关文献

参考文献5

二级参考文献35

  • 1Jin Y H.Particle transport in turbulent buoyant plumes rising in a stably stratified environment[R], 1993.
  • 2Anders Jansson and Lars Olander.Ventilation'94 proceedings of 4th International Symposium on Ventilation for Con 'taminant Control[J].held in Stockholm, 1994(9) :5-9.
  • 3Goodfellow HD.Industrial ventilation[R].ACGIH,2004.
  • 4William L Leffler, Richard Pattarozzi, Gordon Sterling. Deepwater Petroleum Exploration & Production[R]. USA, PennWell Corporation, 2003.
  • 5Yong Bai, Qiang Bai. Subsea Pipelines and Risers[R]. Great Britain, Elsevier Ltd, 2005.
  • 6Ben C Gerwick Jr. Construction of Marine and Offshore Structures[M]. USA, CRC Press, 2007.
  • 7sChristopher West, Stephen Armstrong, Damon MeMillan, et al. S-lay installation of riser fairings for the independence hub[C]//Proceedings of the International Conference on Offshore Mech~ics and Arctic Engineering. 2007(1):515-525.
  • 8Heedo D Yun, Ralf R Peek, Paul R Paslay, et al. Loading history effects for deep-water S-lay of pipelines[J]. Journal of Offshotve Mechanics and Arctic Engineering, 2004, 126(2): 156-163.
  • 9Massimo Pulici, Marian Trifon, Andrei Dumitrescu. Deep water salines installation by using the J-lay method-The blue stream experience[ C] //Proceedings of the International Offshore and Polar Engineering Conference, ISOPE. 2003:585-590.
  • 10Dick Wolbers, Rob Hovinga. Installation of deepwater pipelines with sled assemblies using the new J-lay system of the DCV balder[J]. Journal of Offshore Technology, 2003, 11 (3) : 46-57.

共引文献59

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部