摘要
通过分析河南洛宁抽水蓄能电站工程特点及相关地质条件,梳理得到了引水斜井采用TBM施工的关键技术问题,研究提出了洛宁抽水蓄能电站引水斜井应用TBM的布置方案。综合考虑隧洞功能要求、支护及衬砌厚度、围岩变形量等因素,将引水斜井开挖直径确定为7.2 m,在高水头的抽水蓄能电站推广适用性较好。综合考虑TBM施工方法对围岩分类评价体系的影响、TBM设备支护能力、规程规范要求以及参考类似工程经验,初步拟定了洛宁电站引水斜井开挖支护参数。
Based on the analysis of the engineering characteristics and related geological conditions of Luoning Pumped-storage Power Station in Henan Province,the key technical problems of TBM construction of diversion inclined shaft are summarized,and the layout scheme of TBM construction for the diversion inclined shaft are studied and put forward.Considering the tunnel function requirements,support and lining thickness,and surrounding rock deformation,the excavation diameter of diversion inclined shaft is determined as 7.2 m.It is found that the 7.2 m excavation diameter is suitable for the high head pumped-storage power station.Considering the influence of TBM construction method on surrounding rock classification evaluation system,TBM equipment support capacity,specification requirements and similar engineering experiences,the excavation support parameters of diversion inclined shaft of Luoning Pumped-storage Power Station are preliminarily determined.
作者
张学清
王炳豹
殷康
杜藏
ZHANG Xueqing;WANG Bingbao;YIN Kang;DU cang(Henan Luoning Pumped Storage Co.,Ltd.,Luoyang 471700,Henan,China;Hunan Provincial Key Laboratory of Key Technology on Hydropower Development,Changsha 410014,Hunan,China;PowerChina Zhongnan Engineering Corporation Limited,Changsha 410014,Hunan,China)
出处
《水力发电》
CAS
2022年第2期81-87,共7页
Water Power
关键词
引水斜井
TBM施工
关键技术
开挖支护参数
洛宁抽水蓄能电站
diversion inclined shaft
TBM construction
key technology
excavation support parameters
Luoning Pumped-storage Power Station