摘要
针对西坑水库存在的土坝渗漏问题,提出了几种比选方案,并通过比选采用了塑性混凝土防渗墙作为土坝的防渗技术措施。介绍了塑性混凝土防渗墙的几处设计要点,可为类似工程提供一定的参考和借鉴。
In view of the leakage problem of the earth dam in Xikeng Reservoir,several comparison schemes are put forward,and the plastic concrete cutoff wall is adopted as the anti-seepage technical measure of the earth dam through comparison.This paper introduces several design points of plastic concrete cutoff wall,which can provide some reference for similar projects.