摘要
以福建福清核电一期工程#1、#2已投入商业运行核电机组为实践依据,重点阐述了核电站电气贯穿件在建造阶段的调试步骤与过程,介绍了电气贯穿件调试的目的、原理与方法、过程及验收准则,对以往经验进行总结性集成,为今后核电站调试积累宝贵经验。
Based on the practice of Fujian Fuqing nuclear power phase I project#1,#2 unit which have been put into commercial operation,the commissioning steps and process of electrical penetration parts in nuclear power plant during construction stage are mainly elaborated.The purpose,principle,method,process and acceptance criteria of EPA commissioning are introduced.The previous experience is summarized and integrated,so as to accumulate valuable experience for nuclear power plant commissioning in the future.
作者
李建伟
LI Jianwei(China Energy Engineering Group Co.,Ltd.,Shanghai 200061,China)
出处
《电工技术》
2022年第1期83-85,共3页
Electric Engineering
关键词
电气贯穿件
调试
技术总结
介电强度
泄漏试验
electrical penetration assembly
commissioning
technical summary
dielectric strength
leakage test