银江水电站地处攀枝花市主城区,既是水电工程,也是攀枝花市重大环境基础设施工程。因此在移民安置实施过程中,攀枝花市政府与项目业主达成了移民安置费用9×10^(8)元包干的合作协议,超出部分由攀枝花市政府承担。鉴于此并考虑到银江水电站移民安置与城市建设项目拆迁安置等工作同时进行,为使移民安置政策和地方政策衔接,实现区域征地拆迁工作总体平衡,移民安置工作需结合地方政府实际进行统筹。
Yinjiang Hydropower Station,located in the main urban area of Panzhihua City,is not only a hydropower project,but also a major environmental infrastructure project of Panzhihua City.Therefore,during the implementation of resettlement,the Panzhihua Municipal Government and the project owner have reached a cooperation agreement for resettlement costs of 900 million yuan,the excess of which is borne by the Panzhihua Municipal Government.In view of this and considering that resettlement of Yinjiang Hydropower Station and resettlement of urban construction projects are carried out at the same time,in order to link resettlement policies with local policies and achieve overall balance of regional land acquisition and resettlement work,the resettlement work needs to be coordinated with the actual situation of local governments.
作者
李军磊
朱建波
肖入宾
薛舜
LI Jun-lei;ZHU Jian-bo;XIAO Ru-bin;XUE Shun(Power China Kunming Engineering Corporation Limited,Kunming 650051,China;Panzhihua Poverty Alleviation Development Bureau,Panzhihua 617000,China;Bureau of Agricultural,Rural and Transportation and Water Conservancy,East District of Panzhihua City,Panzhihua 617000,China)
出处
《云南水力发电》
2022年第2期226-229,共4页
Yunnan Water Power
关键词
银江水电站
城市发展
征地拆迁
统筹实施
Yinjiang Hydropower Station
urban development
land expropriation and house removal
overall implementation