瓦斯隧道施工风险评估及处置措施研究 被引量:2

Study on Risk Assessment and Disposal Measures of Gas Tunnel Construction
下载PDF
导出
摘要 从人员、设备、环境及管理角度出发,建立瓦斯隧道施工风险评价体系。依托乘法原理与可拓层次模型,确定L隧道瓦斯风险等级。研究得出:L隧道风险等级评判结果为1.56,瓦斯涌出估算量为2.63 m^(2)/min,瓦斯绝对涌出量为1.79 m^(2)/min,隧道处于危险状态。最后,从施工通风、钻爆作业、电器设备与作业机械、瓦斯预测及监测方面给出危险处置建议。 From the perspective of personnel, equipment, environment and management, the risk evaluation system of gas tunnel construction is established. The gas risk level of L tunnel is determined based on the multiplication principle and extension hierarchy model. The results show that the risk grade evaluation result of L tunnel is 1.56, the estimated gas emission is 2.63 m^(2)/min, the absolute gas emission is 1.79 m^(2)/min, and the tunnel is in a dangerous state. Suggestions on disease treatment are given from the aspects of construction ventilation, drilling and blasting operation, electrical equipment and operation machinery, gas prediction and monitoring.
作者 杨永斌 樊永强 高伟政 王庆 肖伟 YAGN Yongbin;FAN Yongqiang;GAO Weizheng;WANG Qing;XIAO Wei(CCCC Second Highway Engineering Co.,Ltd.,Xi'an Shaanxi 710065)
出处 《河南科技》 2021年第28期80-83,共4页 Henan Science and Technology
基金 中交第二公路工程局科技研发项目(GHTJ-07-QT-046)。
关键词 瓦斯隧道 风险评价 组合赋权 层次可拓模型 现场测试 gas tunnel risk assessment combination weighting hierarchical extension model field test
  • 相关文献

参考文献10

二级参考文献92

共引文献72

同被引文献12

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部