摘要 新建南通—苏州—嘉兴—宁波铁路是国家高速铁路网的重要组成部分,也是长三角地区城际铁路网骨干线路。铁路需穿越苏州工业园区,园区内住宅小区密集,同时分布有大批对振动较敏感的高科技电子、精密仪器企业,应尽量减少对住宅小区和沿线企业的影响。通过对线路走向和敷设方式多方案比选,并对振动评估进行专题论证,最终采用征拆较小、易于实施、有效的集约土地资源,有利于改善园区城市环境的凤里街地下方案。研究表明,高速铁路在通过城区段时,线路走向及敷设方式需结合拆迁、工程投资、噪声振动、环境影响等因素综合确定,虽然地下方案直接工程投资较高,但考虑到征地拆迁影响因素后,总投资与高架方案相差不大,且地下方案对外部环境影响较少,更有利于项目顺利推进。 The newly-built Nantong-Suzhou-Jiaxing-Ningbo Railway is an important part of the national high-speed railway network and a key line of the intercity railway network in the Yangtze River Delta.The railway needs to pass through the Suzhou Industrial Park which is densely populated by residential communities.There are lots of high-tech electronic and precision instrument companies that are sensitive to rail-wheel vibration.Thus,it is necessary to minimize the vibration effects on residential communities and enterprises along the line.Through the comparison of multiple schemes of route direction and laying methods,and special demonstration of vibration assessment,the underground plan along the Fengli Street,which has advantages including low requirement for requisition and demolition,easy-to-implement,effective intensive land resources,conducive to improving the urban environment of the park,was finally adopted.Studies shows that when high-speed railways pass through urban sections,the route and laying methods need to be comprehensively determined in consideration of factors such as demolition,project investment,noise and vibration,and environmental impact.Although the direct engineering investment of the underground scheme is relatively high,taking account of the factors such as land acquisition and demolition,the total investment is similar with the viaduct scheme and it has less impact on the external environment.
作者 林海波 Lin Haibo(China Railway Engineering Design and Consulting Group Co.,Ltd.,Beijing 100055,China)
出处 《铁道勘察》 2022年第1期45-51,共7页 Railway Investigation and Surveying
关键词 通苏嘉甬铁路 高架方案 地下方案 振动影响 方案比选 Nantong-Suzhou-Jiaxing-Ningbo Railway viaduct scheme underground scheme vibration influence scheme comparison
  • 相关文献

参考文献7

二级参考文献31

  • 1王立暖,马志富,杨贵生.铁路隧道防灾救援技术研究[J].铁道标准设计,2007,27(z1):50-55. 被引量:26
  • 2吴伟.平原及山区高速铁路选线的控制因素[J].铁道勘察,2010,36(1):87-89. 被引量:4
  • 3安玉红.铁路隧道防灾救援疏散工程设计研究[J].石家庄铁道大学学报(自然科学版),2013,26(S2):99-104. 被引量:16
  • 4刘春明.铁路选线应综合考虑的主要问题[J].铁道勘察,2007,33(2):69-72. 被引量:34
  • 5[2]铁道第三勘察设计院.胶州至新沂铁路可行性研究报告[R].天津:铁道第三勘察设计院,2000
  • 6[3]铁道第三勘察设计院.太原至中卫(银川)铁路初步设计[R].天津:铁道第三勘察设计院,2006
  • 7成昆铁路技术总结委员会.成昆铁路线路、工程地质及路基(第二册)[M].北京:人民铁道出版社,1980.
  • 8中铁二院工程集团有限责任公司.新建铁路织金至毕节线可行性研究总说明书[Z].成都:中铁二院工程集团有限责任公司2011.
  • 9中铁二院工程集团有限责任公司.改建铁路成都至昆明线米易至攀枝花段可行性研究总说明书[Z].成都:中铁二院工程集团有限责任公司,2011.
  • 10中铁二院工程集团有限责任公司.改建铁路成都至昆明线永仁至广通段可行性研究总说明书[Z].成都:中铁二院工程集团有限责任公司,2011.