基于上海某隧道工程围护结构所采用的3种地下连续墙接头形式的施工过程,结合现场实际形成的施工数据和围护结构设计图纸,从施工工艺、施工时间、质量管控及墙面渗漏情况等进行综合对比分析,得出一定的结论,以作后续施工参考经验。
Based on the construction process of three types of diaphragm wall joints used in the enclosure structure of a tunnel project in Shanghai, combined with the actual construction data and enclosure structure design drawings, a comprehensive comparative analysis is carried out from the aspects of construction technology,construction time, quality control and wall leakage, and some conclusions are drawn for reference experience in subsequent construction.
出处
《建筑技术开发》
2022年第6期118-120,共3页
Building Technology Development
关键词
地下连续墙
接头形式
围护结构
墙面渗漏
underground diaphragm wall
joint
enclosure structure
wall leakage