摘要
通过对盖孜水电站蜗壳及外围混凝土结构联合承载力进行有限元计算分析,假定在3.2 MPa的充水保压值下,对蜗壳的打压顺序进行分析,通过计算最终确定先打压后浇筑的施工顺序。
Through the finite element analysis and calculation of the combined bearing capacity of spiral case and surrounding concrete structure of Gaiz Hydropower Station,the pressure sequence of spiral case is analyzed under the assumption of 3.2MPa water filling pressure holding value.Through calculation and analysis,the construction sequence of first pressing and then pouring is finally determined.
作者
钱军刚
QIAN Jungang(Xinjiang Water Conservancy and Electricity Survey and Designing Institute,Urumqi 830000,China)
出处
《广东水利水电》
2022年第4期95-99,共5页
Guangdong Water Resources and Hydropower
关键词
金属蜗壳
充水保压
打压顺序
holding and pressing of metal spiral case
water filling and pressurizing
sequence of filling