摘要
介绍了玉林市龙云灌区蟠龙水库上、下坝址方案的详细布置。从节省投资、布置合理性、施工方便性等多角度对两个方案进行对比分析,为蟠龙水库选择合理的坝址,并推荐上坝址方案为执行方案。项目建成后,将统筹解决该区域的水资源问题。
An introduction was made on the detailed layout of two dam site schemes of Panlong Reservoir in the Longyun Irrigation Zone of Yulin City. The upper and lower dam site schemes were compared in respects of investment saving, layout rationality, construction convenience etc, based on which the upper dam site scheme was recommended. After the completion of this project, the problem of water resources in this region will be solved as a whole.
作者
胡京川
HU Jing-chuan(Guangxi Water and Power Design Institute Co.,Ltd.,Nanning 530023,China)
出处
《广西水利水电》
2022年第2期51-54,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
蟠龙水库
泄洪闸坝
鱼道
坝址
玉林市
Panlong Reservoir
flood discharging sluice dam
fish way
dam site
Yulin City