1000 kV同塔双回输电线路短接技术研究及应用 被引量:1

Research and Application of Short-connection Technology for 1000 kV Transmission Line with One Tower and Double Circuits
下载PDF
导出
摘要 长治1000 kV变电站配套电厂1000 kV送出工程是长治—南阳—荆门1000 kV特高压输电工程重要配套电源项目。由于工程建设时序的需要,需在赵庄电厂外将两回线路短接以设置临时过渡方案,以满足高河电厂先行送电需求。常规短接方案电厂停电时间长,重复进场施工造成协调难度极大,不利于工程建设。通过在赵庄电厂外双回路终端塔上加装T型跳线横担,实现了两回线路导线短接,经三维仿真校验,电气距离均满足规程规范要求。 The 1000 kV transmission project of Changzhi 1000 kV substation supporting power plant is an important supporting power supply project of Changzhi-Nanyang-Jingmen 1000 kV UHV transmission project.Due to the timing requirement of the project construction,it is necessary to short-circuit the two circuits outside the Zhaozhuang Power Plant to set up a temporary transition plan,so as to meet the demand of advanced power transmission of Gaohe Power Plant.The power outage time of conventional short-circuit scheme is long and repeated construction on site causes great difficulty in coordination,which is not good for engineering construction.By adding T-type jumper cross-arm to double-circuit terminal tower outside Zhaozhuang Power Plant,short connection of two-circuit wire is realized.It is verified by 3-D simulation that the electrical distance meets the requirements of the procedures and regulations.
作者 周波 田军涛 刘波 刘杰 杨莉媛 刘慧娟 ZHOU Bo;TIAN Juntao;LIU Bo;LIU Jie;YANG Liyuan;LIU Huijuan(China Energy Engineering Group Shanxi Electric Power Engineering Co.,Ltd.,Taiyuan,Shanxi 030001,China)
出处 《山西电力》 2022年第2期23-25,共3页 Shanxi Electric Power
基金 中国能源建设集团山西省电力勘测设计院有限公司资助项目(14-K2021-21-D07)。
关键词 1000 kV T型横担 临时短接 T型耐张线夹 扩径导线 1000 kV T-type cross-arm temporary short connection T-type strain clamp expanded diameter conductor