期刊文献+

基于BIM技术的风管制作与安装过程中损耗率的控制

Loss Rate Control in the Process of Air Duct Production and Installation based on BIM Technology
下载PDF
导出
摘要 在大型机电安装工程暖通系统安装是机电工程的重要部分,为切实提高机电安装工程的效率、保证工程进度、降低施工成本。通过应用BIM技术对机电管线进行二次深化设计合理优化管线布局,对风管位置进行准确定位,为风管工厂化预制加工打下基础,同时保证后期风管安装过程中风管损耗率的有效控制,具有较好的经济效益。本文结合具体工程实例,阐述具体的实施方法。 The installation of HVAC system in large-scale mechanical and electrical installation project is an important part of mechanical and electrical engineering, in order to effectively improve the efficiency, ensure the project progress, and reduce the construction cost of mechanical and electrical installation engineering. Through the application of BIM technology for the second deepening design of mechanical and electrical pipelines, the pipeline layout has been optimized reasonably, and air duct locations have been positioned accurately, which lays a foundation for the industrialized prefabrication and processing of air duct, ensures the effective control of air duct loss rate in the later installation process, and achieves good economic benefits.Combined with a concrete project example, this paper expounds the specific implementation method.
作者 聂昆 Nie Kun(First Construction Development Co.,Ltd.,Beijing City Construction,Beijing,101100)
出处 《建设科技》 2022年第8期30-33,共4页 Construction Science and Technology
关键词 BIM技术 风管预制加工 损耗率 BIM technology Air duct prefabrication loss rate
  • 相关文献

参考文献3

二级参考文献9

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部