摘要
文章以重庆至黔江高铁清水坪乌江大桥(96+240+96)m连续钢桁梁-拱组合体系桥面系设计为工程实例,从荷载效应、材料用量等多个方面,对比分析了钢-混凝土板组合桥面系和正交异性板桥面系,结合受力特点和工期、工艺等要求,提出正交异性板方案是一个合理的选择,进而提出正交异性板桥面系的设计方法,以供参考。
Taking the bridge deck system design of(96 + 240 +96) m continuous steel truss girder-arch composite system of Qingshuiping Wujiang Bridge of Chongqing-Qianjiang High-speed Railway as an engineering example,this paper compares and analyzes the steel-concrete slab composite bridge deck system and orthotropic plate bridge deck system from the aspects of load effect and material consumption,etc.Combined with the stress characteristics,construction period and process requirements,it is proposed that the orthotropic plate scheme is a reasonable selection,and then the design method of orthotropic plate bridge deck system is proposed for reference.
作者
陈宇
Chen Yu(China Railway Eryuan Engineering Group Co.,Ltd.,Chongqing 400023)
出处
《工程技术研究》
2022年第5期165-167,共3页
Engineering and Technological Research
关键词
高速铁路
钢桁梁-拱
桥面系设计
high-speed railway
steel truss girder-arch
bridge deck system design