摘要 以北京地铁8号线三期工程王府井北站-王府井站区间隧道近距离下穿懋隆黄金砌体结构建筑物为背景,通过对建筑物现状调查、检测和评估,确定了建筑物变形控制标准。以砌体结构房屋局部倾斜和最大沉降量为指标,分析了降水导洞和区间隧道施工对临近懋隆黄金的影响。研究结果表明:采用数值模拟方法,分析其在自重作用下发生的变形情况,作为建筑物建成后的累计变形,可以为建筑物变形控制指标的确定提供参考依据;降水导洞下穿砌体结构建筑物的施工过程中,采用的超前加固措施,可以有效减少施工对地表建筑物的影响,确保降水导洞和区间隧道施工过程中地表建筑物的结构安全。 Maolong gold masonry structure building was crossed underneath with a short-distance by the running tunnel between Wangfujing North Station and Wangfujing Station of Phase III of Beijing Metro Line 8.The deformation control criteria were determined by investigation,testing and evaluation of the building present situation.Local inclination and maximum settlement of masonry structure building were taken as indexes,the impact of dewatering pilot and running tunnel construction on adjacent Maolong gold building was analyzed.The results show that based on the numerical simulation method,the deformation resulted from self-weight of building was analyzed and taken as cumulative deformation after the construction,this could be the reference to determine deformation control index.During construction process of dewatering pilot crossing underneath masonry structure building,the pre-reinforcement measurement can effectively reduce the impact of construction.The structural safety of building can be ensured during construction of dewatering pilot and running tunnel.
作者 张志学 ZHANG Zhixue(China Railway 16th Bureau Group Metro Engineering Co.,Ltd.,Beijing 101116,China)
出处 《国防交通工程与技术》 2022年第3期38-42,25,共6页 Traffic Engineering and Technology for National Defence
关键词 地铁隧道 下穿建筑物 砌体结构 降水导洞 施工影响 metro tunnel cross underneath building masonry structure dewatering pilot construction influence
  • 相关文献

参考文献5

二级参考文献43

共引文献38

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部