摘要
在铁路复线改造施工中,我们经常会遇到需要设置临时过渡便线的情况,此时,需要对既有铁路与新建铁路连接采取过渡连接。优秀的改建铁路过渡方案可以大幅度减少因施工造成的铁路运能损失并减少施工工作量,因此,过渡方案的选择,是营业线路改建施工的重要环节之一。本文主要以柳州动车存车场铁路工程建设实例,以实际情况为基准,各项规范、技术要求为准绳,与大家共同学习探讨铁路线路过渡方案的确定与实际应用。
In the construction of railway double-track reconstruction,we often encounter the need to set up a temporary transitional line.At this time,it is necessary to adopt a transitional connection between the existing railway and the new railway.An excellent transition plan for railway reconstruction can greatly reduce the loss of railway transportation capacity caused by construction and reduce the construction workload.Therefore,the choice of transition plan is one of the important links in the reconstruction and construction of business lines.This paper mainly takes the example of railway engineering construction in Liuzhou EMU depot,takes the actual situation as the benchmark,and various specifications and technical requirements as the criterion,and discusses the determination and practical application of the railway line transition plan with everyone.
作者
霍伟
HUO Wei(The 4th Engineering Co.,Ltd.of China Railway 25th Bureau Group,Liuzhou 545007,China)
出处
《价值工程》
2022年第18期138-140,共3页
Value Engineering
关键词
改建铁路
过渡线路
方案
实际应用
reconstruction of railway
transition line
scheme
practical application