摘要
浮托顶推法是一种创新的施工方法,它将浮托法与顶推法相结合,具有施工速度快、材料节约、占用通航河道时间短、对河道无污染等特点,适用于大跨径的跨河或沿海桥梁的架设施工。本文总结了多点浮托顶推在钢箱梁架设时的方法,包括技术原理、工艺流程、操作要点等,并采用理论结合实际的方法,以实际工程为例,探讨了浮托顶推在施工时应注意的难点以及处置方式。实践表明:通过浮托顶推法架设钢箱梁,不仅加快了施工进度,同时缩短了封航时间,带来了良好的社会效益和经济效益。
Floating bracketand jack-in method is an innovative construction method.It combines floating bracketmethod with jacking method,and it has the characteristics of fast construction speed,material saving,short occupation of navigable rivers,and no pollution to the rivers.It is suitable for construction of large-span bridges across rivers or coastal bridges.In this article,the application of the multi-point floating bracket and jack-in method in the erection of steel box girder is introduced,including the construction technology principle,process flow,operating points,etc.,the method of combining theory with practice is adopted,and taking actual engineering as an example,the multi-point floating bracket and jack-in method is discussed In terms of difficulties and disposal methods that should be paid attention to during construction.The practice show that erection of the steel box girder by the floating bracket and jack-in method not only speeds up the construction progress,but also shortens the closure time,bringing good social and economic benefits.
作者
张猛
ZHANG Meng(China Railway 24th Bureau Group Co.,Ltd.,Shanghai200000,China)
出处
《工程建设》
2022年第4期56-62,共7页
Engineering Construction
关键词
混合梁桥
大跨径
钢箱梁
多点浮托
顶推
hybrid girder bridge
long-span
steel box girder
multi-point floating bracket
jack-in