城市轻轨工程节段箱梁的架设安装

Erection and Installation of Segmental Box Girder in Urban Light Rail Project
下载PDF
导出
摘要 在澳门C370轻轨线路建设过程中,由于工作节点(里程碑)多、工期紧张工程量大,为了在完成建设任务,高架桥设计采用场外预制,现场节段拼装方案,节省了现场用地并提高了施工速度。本文以C370轻轨线路节段箱梁的架设安装所用的施工工艺,技术安装设备等内容为例,对城市轻轨工程节段箱梁安装进行全方位的介绍。 Because of many milestones are set and the construction schedule is nervous during the construction of Macao C370 light rail project,the viaduct girders adopts the scheme of off-site prefabrication and on-site segment erection method which saves on-site land and improves the construction speed.Taking the construction technology and installation equipment used in the erection and installation of section box girder of C370 light rail line for example,this paper comprehensively introduces construction method of segmental box girder in urban light rail project.
作者 张耀栋 Zhang Yaodong(CCCC fourth Navigation Engineering Bureau Co.,Ltd.,Guangzhou 510290,China)
出处 《科学技术创新》 2022年第17期105-108,共4页 Scientific and Technological Innovation
关键词 轻轨施工 架桥机 精确度 安装工艺 Light rail construction Bridge erecting machine Precision Installation technology
  • 相关文献

参考文献5

二级参考文献44

共引文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部