刚果(金)某大型铜钴矿磨矿工艺优化研究 被引量:1

Research on optimization of grinding process of a large copper-cobalt mine in D R Congo
原文传递
导出
摘要 刚果(金)某大型铜钴矿项目碎磨系统设计为SAB流程,自投产以来出现系统处理量波动大、球磨机运行负荷率过低、旋流器及球磨机循环负荷重、钢球单耗偏高等问题。为此对磨矿工艺进行了详细的流程考察,利用JKSimMet仿真软件分析流程考察数据认为,矿石硬度波动大、半自磨出料圆筒筛堵塞、球磨机循环负荷大是主要原因,进而有针对性地提出了系统工艺优化和技术改造建议。 The comminution system of a large copper-cobalt mine in D R Congo was designed as SAB circuit,it had undergone the problems such as large throughput fluctuation,over-low operating load ratio of the ball mill,heavy circulating load of the cyclone and the ball mill,high specific consumption of the steel ball etc since put into use.Therefore,the grinding process was surveyed in detail.The analysis results with the aid of JKSimMet simulation software indicated the large fluctuation of ore hardness,the blockage of the trommel behind the SAG mill and the heavy circulating load of the ball mill were the main causes,and the targeted suggestions about optimization of the system operation and technical innovation were put forward.
作者 兰川 刘佳鹏 徐敬元 董宏军 杨军 周统中 LAN Chuan;LIU Jiapeng;XU Jingyuan;DONG Hongjun;YANG Jun;ZHOU Tongzhong(Norin Mining Limited,Beijing 100053,China)
出处 《矿山机械》 2022年第5期30-34,共5页 Mining & Processing Equipment
关键词 磨矿工艺 碎磨流程 半自磨机 球磨机 工艺优化 grinding process comminution circuit SAG mill ball mill process optimization
  • 相关文献

参考文献4

二级参考文献43

  • 1许伟,杨黎升,唐新民,吴照银.半自磨机钢球大小的研究[J].冶金设备,2007(2):19-22. 被引量:15
  • 2唐新民.磨机全推送给料器[P].中国专利:ZL200820008836.2009-01-21.
  • 3唐新民.湿式磨机螺旋溢流分级出料器[P].中国专利:200920172105.X,2010-02-03.
  • 4Morrison RD,Richardson JM. JK SimMet-a simulator for analysis,optimasation and design of comminution circuits[C]. Proc. Mineral Processing Plant Design, Practice and Control Conference, SME, Vancouver, 2002,442- 460
  • 5Lynch AJ. Mineral crushing and grinding circuits: Their simulation,optimisation design and control[M]. New York: Elsevier, 1977
  • 6Napier-Munn TJ, Morrell S, Morrison RD, Kojovic T. Mineral comminution circuits: Their Operation and optimisation[M] Brisbane:JKMRC, University of Queensland,1996
  • 7Shi F, Kojovic T, Larbi- Bram S, Manlapig EV. Recent developments in ore breakage characterization[C]. Paper to be presented at ⅩⅩⅣ IMPC, Bering, 2008
  • 8Schwarz S,Alexander DJ, Whiten W J, Franzidis J P, Harris M C. JKSimFloat V6: Improving flotation circuit performance and understanding[C]. Proc. ⅩⅩⅢ IMPC, 2006,3 : 1717- 1722
  • 9Harris MC, Runge KC, Whiten WJ,Morrison RD. JKSimFloat as a practical tool for flotation process design and optimisation[C]. Proc. Mineral Processing Plant Design, Practice and Control Conference, SME, Vancouver, 2002,461 - 478
  • 10Alford RA. Modelling of single flotation column stages and column circuits[J]. Internatinal Journal of Mineral Processing, 1992,36:155-174

共引文献34

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部