基于时标网络计划实际进度前锋线的工程项目进展偏差分析

Analysis of Engineering Project Progress Deviation Based on Time-Scale Network Planning Actual Progress Front Line
下载PDF
导出
摘要 项目建设过程中运用双代号时标网络计划实际前锋线原理,利用赢得值法分析项目各个进度节点投资和总工期完成情况偏差,优化建设项目网络图,达到建设工程投资和进度的最佳效果,本文以此为研究对象进行探讨。 In the process of project construction,the principle of the actual front line of the network plan with double-code time-scale is used,and the earned value method is used to analyze the deviation between the investment at each progress node and the completion of the total construction period,and to optimize the network diagram of the construction project,so as to achieve the best effect of the investment and progress of the construction project,which is the research object of this article.
作者 张根 Zhang Gen(Yanbian County Urban and Rural Construction Development Center,Panzhihua 617199,Sichuan Province,China)
出处 《建筑与装饰》 2022年第10期184-186,共3页 Construction & Decoration
关键词 时标网络计划 实际进度前锋线 偏差分析 赢得值 time-scale network planning actual progress front line deviation analysis earned value
  • 相关文献

参考文献2

二级参考文献13

共引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部