摘要
基于西安地铁某高架车站工程,分析比较了混凝土现浇施工、预制板房和节段拼装三种应用于钢筋混凝土结构的施工方法,并结合工程实际情况,采用现浇施工方法进行施工组织。
Based on a elevated station project of Xi'an Metro,this paper analyzes and compares the construction methods of concrete cast-in-place construction,prefabricated board house and segmental assembly for reinforced concrete structure,and considers the construction organization of this station by using castin-place construction method combined with the actual situation of the project.
作者
卢立红
高苏
LU Lihong;GAO Su(Shandong Transportation Institute,Shandong Jinan 250031 China)
关键词
高架车站
现浇施工
施工组织
elevated station
cast-in-place construction
construction organization