浅析防震缝施工中工程质量事故处理措施和施工方案 被引量:2

Analyze the Handling Measures and Construction Scheme of Engineering Quality Accidents in the Construction of Seismic Joints
下载PDF
导出
摘要 防震缝在施工过程中容易存在缝宽不满足要求的情况,后期处理难度较大,费用较高。利用结构计算结果,制定合理的加固方案,有效地解决了防震缝宽度不足的具体工程质量事故。该工程利用分区置换、结构回顶和支撑措施进行了处理,节约了工期和成本,为该类工程质量事故处理提供参考的措施,并对后续施工方案提供有效的建议。 In the construction process of shockproof joint,it is easy to have the situation that the joint width does not meet the requirements,and the later processing is difficult and the cost is high.Using the calculation results of the structure,make a reasonable reinforcement scheme;effectively solve the specific engineering quality accident of insufficient width of the seismic joints. The project uses zoning replacement,structural jacking and support measures to effectively deal with,save the construction period and cost,provide reference measures for the handling of such engineering quality accidents,and provide effective suggestions for the subsequent construction scheme.
作者 黄云力 张前奇 鄢欢 张翔 彭怀 黄海斌 HUANG Yunli;ZHANG Qianqi;YAN Huan;ZHANG Xiang;PENG Huai;HUANG Haibin(Chongqing Lingfan Testing Technology Co.,Ltd.,Chongqing 400112,China;Chongqing University of Science and Technology,Chongqing 401331,China)
出处 《工程质量》 2022年第6期66-70,共5页 Construction Quality
关键词 工程质量事故 防震缝 构件置换 engineering quality accident seismic joint component replacement
  • 相关文献

参考文献5

二级参考文献10

共引文献41

同被引文献4

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部