摘要
本文以某铁路牵引变电所建设方案为例,通过对铁路牵引变电所直采直送系统工程应用涉及的通信接入系统、调度自动化系统、铁路与国网的分工界面等方面的详细阐述,总结出现有铁路牵引变电所直采直送系统建设方案存在问题,提出建议解决方案,以期能为新线铁路牵引变电所建设提供参考。
Taking the construction scheme of a railway traction substation as an example,this paper summarizes the problems in the construction scheme of the direct acquisition and transmission system of existing railway traction substation by elaborating the communication access system,dispatching automation system,and the interface between railway and state grid involved in the engineering application of the direct acquisition and transmission system of railway traction substation,and proposes suggestions and solutions accordingly,which are intended to provide reference for the construction of traction substations for new railways.
作者
王峻峰
WANG Junfeng(Chengdu-Lanzhou Railway Co.,Ltd.,Chengdu 610072,China)
出处
《高速铁路技术》
2022年第3期68-71,90,共5页
High Speed Railway Technology
关键词
铁路牵引变电所
直采直送
通信接入
调度自动化
railway traction substation
direct acquisition and transmission
communication access
dispatching automation