期刊文献+

南宁富水砂层盾构施工变形规律分析及控制措施研究

Study on Deformation Law and Control Measures of Shield Tunneling in Nanning Water-Rich Sand Stratum
下载PDF
导出
摘要 以南宁地铁某区间为研究对象,运用理论分析、现场监测和数值模拟相结合的手段进行研究,利用数值模拟软件模拟盾构机施工过程,分析了不同盾构掘进参数对沉降的影响,建立盾构施工参数与沉降的关系,通过与实测数据的对比分析总结了富水砂层盾构施工地表沉降的变形规律,提出富水砂层盾构施工的地表沉降控制措施。 Taking a certain section of Nanning Metro as the research object,this paper uses the means of theoretical analysis,field monitoring and numerical simulation to study,uses numerical simulation software to simulate the construction process of shield tunneling machine,analyzes the influence of different shield tunneling parameters on the settlement,and establishes the relationship between shield tunneling parameters and settlement.By comparing with the measured data,the deformation law of surface settlement of shield construction in water-rich sand layer is summarized,and the control measures of surface settlement of shield construction in water-rich sand layer are given,which can provide reference for similar projects.
作者 廖鹏 LIAO Peng(Beijing Urban Construction Survey,Design and Research Institute Co.Ltd.,Beijing 100101,China;Beijing Key Laboratory of Deep Foundation Pit Geotechnical Engineering for Urban Rail Transit,Beijing 100101,China)
出处 《工程建设与设计》 2022年第10期177-179,共3页 Construction & Design for Engineering
关键词 富水砂层 盾构施工 变形规律 控制措施 water-rich sand layer shield construction deformation law control measures
  • 相关文献

参考文献5

二级参考文献73

共引文献196

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部